Steel Erection guidelines site preparation…
Site Layout, Site-specific Erection Plan and Construction Sequence [29 CFR 1926.752]
Proper communication between the controlling contractor and the steel erector prior to the beginning of the steel erection operation is essential to employee safety. Many accidents involving collapse could have been averted had adequate pre-erection communication and planning occurred. The following requirements for site preparation, including site layout, pre-planning of overhead hoisting operations, and (in some cases) site-specific erection plans, have been made to ensure safety during the initial stages of steel erection.
- Approval and Commencement
- Site Layout
- Pre-Planning
- Site-Specific Erection Plan
Approval and Commencement
- The controlling contractor must provide written notification to the steel erector ensuring that [29 CFR 1926.752(a)]:
- Concrete in footings, piers, and walls has been cured to a level that will provide adequate strength to support any forces imposed during steel erection. [29 CFR 1926.752(a)(1)]
- Anchor bolt repairs, replacements and modifications were done with the approval of the project Structural Engineer of Record (SER). [29 CFR 1926.752(a)(2) and 1926.755(b)(1)]
- A steel erection contractor may not erect steel without the above written notification. [29 CFR 1926.752(b)]
Site Layout
- In order for the steel erector to perform necessary operations in a safe manner, the controlling contractor must provide and maintain [29 CFR 1926.752(c)]:
- Access roads into and through the site that are adequate for safe delivery and movement of [29 CFR 1926.752(c)(1)]:
- Derricks
- Cranes
- Trucks
- Other necessary equipment
- The material to be erected
- Access roads into and through the site that are adequate for safe delivery and movement of [29 CFR 1926.752(c)(1)]:
- Means and methods for pedestrian and vehicular control. [29 CFR 1926.752(c)(1)]
- Adequate space for the safe storage of materials and the safe operation of the erector’s equipment, which is [29 CFR 1926.752(c)(2)]:
- Firm
- Properly graded
- Drained
- Readily accessible to the work
EXCEPTION: This provision does not apply to roads outside of the construction site.
Pre-Planning
All hoisting operations in steel erection must be pre-planned to ensure that [29 CFR 1926.752(d)]:
- Employees are not working directly below suspended loads, except for [29 CFR 1926.753(d)(1)]:
- Employees engaged in the initial connection of the steel. [29 CFR 1926.753(d)(1)(i)]
- Employees necessary for the hooking and unhooking of the load. [29 CFR 1926.753(d)(1)(ii)]
- Where employees must work under the load, the materials being hoisted are:
- Rigged to prevent unintentional displacement. [29 CFR 1926.753(d)(2)(i)]
- Prevented from slipping by the use of hooks with self-closing safety latches or their equivalent. [29 CFR 1926.753(d)(2)(ii)]
- Rigged by a qualified rigger. [29 CFR 1926.753(d)(2)(iii)]
Site-Specific Erection Plan
Employers may elect, because of conditions specific to the worksite, to develop alternate means of providing the employee protection required in 29 CFR 1926.753(c)(5), 29 CFR 1926.757(a)(4) or 29 CFR 1926.757(e)(4). If a site-specific erection plan is used, it must [29 CFR 1926.752(e)]:
- Be developed by a qualified person.
- Be available at the work site.
Components of a site-specific erection plan. [Non-mandatory Appendix A]
A site-specific erection plan is developed during one or more pre-construction conferences and site inspections involving the erector, the controlling contractor, and others such as the project engineer and the fabricator. In this process, the following elements are considered:
- The sequence of erection activity, developed in coordination with the controlling contractor, including the following:
- Material deliveries
- Material staging and storage
- Coordination with other trades and construction activities
- A description of the crane and derrick selection and placement procedures, including the following:
- Site preparation
- Path for overhead loads
- Critical lifts, including rigging supplies and equipment
- A description of steel erection activities and procedures, including the following:
- Stability considerations requiring temporary bracing and guying.
- Erection bridging terminus point.
- Notifications regarding repair, replacement and modifications of anchor rods (anchor bolts).
- Columns and beams (including joists and purlins).
- Connections
- Decking
- Ornamental and miscellaneous iron
- A description of the fall protection procedures that will be used to comply with 29 CFR 1926.760.
- A description of the falling object protection procedures that will be used to comply with 29 CFR 1926.759.
- A description of the special procedures required for hazardous non-routine tasks.
- A certification for each employee who has received training for performing steel erection operations as required by 29 CFR 1926.761.
- A list of the qualified and competent persons.
- A description of the procedures that will be utilized in the event of rescue or emergency response.
In addition, the plan should include identification of the site and project, and be signed and dated by the qualified person(s) responsible for its preparation and modification.
Shared from: Occupational Safety and Health Administration,
https://www.osha.gov/SLTC/etools/steelerection/siteprep.html
Steel Erection Bid Wizard
Join dozens of your peers that have revolutionized the way they estimate. Take your estimating department digital with Steel Erection Bid Wizard. Only software on the market made for Erectors by an Erector.
Steel Erection Bid Wizard is a fully functional Windows – based software package. Estimate your bids more quickly and easier than ever before.
Benefits Of The Steel Erection Bid Wizard
- Reduce the time it takes to estimate by 50% or more
- Tried & true production rates for labor, crane & weld time
- You can easily adjust production rates to fit your company
- More than 300 built-in tasks
- Ability to create your own tasks and add new categories
- Generate one-touch proposals
- Integrate with multiple takeoff software’s
- Peace of mind
Vince Hughes, Creator
Steel Estimating Solutions
Phone: 505-249-2390